November 17, 2026

Embodied Carbon Is No Longer “Future LEED”

Lauren-Richardson-Sustainability-Associate-Green-Badger-1

by Lauren Richardson
Sustainability Manager at Green Badger

For a long time, embodied carbon was one of those things everybody agreed was important, but almost nobody actually had to deal with it. It lived in conference keynotes and pilot credits. Then it quietly disappeared from the project checklist.

That’s over. Embodied carbon is now a prerequisite in LEED v5 and a mandatory requirement in California’s building code, and more states are coming. If you’re a GC or a sustainability manager, this is a line item on your projects today. Not someday. Today.

In our last post, Embodied Carbon on Real Projects: What Teams Are Actually Tracking, we covered what field teams are tracking day to day. This one goes a level deeper: what the rules actually require, where LEED v5 and CALGreen line up, and how to build one process that checks both boxes.

Quick Refresher: Why Embodied Carbon Is Different

Embodied carbon is the carbon from making, moving, and installing your building materials. It’s the footprint of your concrete, steel, glass, and insulation before the building ever turns on a light.

What makes it different from energy is timing. Operational carbon can be tuned over decades with better controls, retrofits, and a cleaner grid. Embodied carbon gives you exactly one shot. And that shot is procurement. Once the concrete is poured, the carbon is locked in.

That’s why the rules focus on the buy. And it’s why contractors are at the center of this.

LEED v5: From “Nice Points” to “No Certification Without It”

Under LEED v4 and v4.1, embodied carbon was optional. You could chase a WBLCA credit, collect EPDs for points, or skip it all and still certify.  LEED v5 closes that door. Embodied carbon now shows up in two places.

The Prerequisite: Quantify and Assess Embodied Carbon (MRp2)

This is the big one. MRp2 is mandatory. Every LEED v5 project has to measure its embodied carbon.  The prerequisite doesn’t ask you to hit a reduction target. It asks you to know your number. In practice, that means:

  • Calculating the embodied carbon of your major building elements: structure, enclosure, and hardscape
  • Using actual material quantities and real product carbon data
  • Identifying the biggest carbon drivers on the project

For contractors, that means someone has to collect installed quantities by material and manufacturer and pull the EPDs that go with them.

The Credit: Reduce Embodied Carbon (MRc2)

Once you’ve measured, LEED v5 rewards you for doing better. MRc2 awards points for coming in below a baseline, and there are two main ways to get there.

Path 1: Whole-building LCA. The design team models the building and compares it to a baseline. This one lives mostly with the design side.

Path 2: Product-based comparison. The team compares the GWP of installed products, pulled from their EPDs, against industry baselines like the Carbon Leadership Forum (CLF) material baselines. This path lives in procurement and submittals. Which is where the GC has the most control.

Either way, the credit is based on the actual products you buy, not the design-stage estimate. Early numbers are fine for setting a baseline, but the procurement-stage actual is the number that counts.

A quick note on baselines: A baseline is just the industry average for a material, the number you’re trying to beat. Think of it like a fuel economy sticker. Before you know if a specific car is efficient, you need to know what’s normal for that class of vehicle. The CLF does the same thing for building materials; it collects EPD data from thousands of products and publishes an average GWP by material category. MRc2 isn’t asking “is your carbon number low in absolute terms?” It’s asking, “Is your product better than typical?” The CLF baseline is that yardstick.

CALGreen: Embodied Carbon Is Now Code

If LEED v5 is the carrot, CALGreen is the rulebook. In summer 2023, California became the first state to mandate embodied carbon reduction in its building code. That’s a big deal. LEED is voluntary. The building code is not.

Who Has to Comply

Any nonresidential new construction, alteration, or addition over 50,000 square feet. And that square footage counts new and existing construction combined, so an addition to a large existing building can trigger it.

The Three Compliance Paths

CALGreen gives you three options.

  1. Building reuse. Keep at least 45% of an existing structure and its exterior. Not building new is often the lowest-carbon move available.
  2. Whole-building LCA. Show at least a 10% embodied carbon reduction compared to a reference building of similar size and function, using a cradle-to-grave WBLCA. This aligns with the LEED v4/v4.1 life cycle credit and can help projects earn up to 4 LEED points depending on the version.
  3. Product GWP limits (prescriptive). Show that key materials come in under maximum GWP values. Structural steel, rebar, concrete, flat glass, and mineral wool board insulation. For concrete, limits are set by strength class — standard ready-mix up to 2,400 psi is capped at 450 kg CO₂e per cubic meter, 2,500–3,499 psi at 489, and 3,500–4,499 psi at 566.

For most GCs, the prescriptive path feels the most familiar. It’s a submittal review with one more number to check. The catch is that you need the number before you buy, which means the EPD has to be in hand before the mix gets approved.

Where LEED v5 and CALGreen Overlap

If you’re building a LEED v5 project in California, you’re dealing with both. Here’s the good news: the data is almost the same.

  • Installed material quantities by product and manufacturer
  • Product-specific EPDs
  • GWP values in consistent, comparable units
  • A clear baseline to compare against

The difference is what each one does with the data. CALGreen asks, “Did you pass?” LEED v5 asks, “How did you do it and can you do better?”

The smartest move is to build one data set that serves both. Collect it once, organize it by structure, enclosure, and hardscape, and use it for code compliance and LEED documentation at the same time.

Other States Are Moving Too

And it’s not just California. Other states are starting to put real teeth behind embodied carbon, and they’re doing it through Buy Clean legislation. California got the ball rolling with its Buy Clean California Act, setting actual GWP limits on structural steel, rebar, flat glass, and mineral wool insulation for public projects. Since then, Colorado, Maryland, Michigan, New York, and Washington have all jumped in with their own versions, targeting the same core materials and requiring EPDs to back it up. The federal government is following suit; GSA and DOT have both moved to weave Buy Clean requirements into public procurement.

Here’s why this matters if you’re working in LEED v5: the EPDs, the CLF baselines, the material categories — it’s the same infrastructure. If you’re building a solid MRc2 workflow, you’re already doing the work Buy Clean compliance will require. You’re not just chasing a plaque. You’re getting ahead of where the whole industry is heading.

What This Means in Practice

Our last post covered the field tactics in detail, so here’s the short version framed around the new requirements.

  • Confirm requirements at kickoff. Is this a LEED v5 project? Is it over the CALGreen threshold? Which compliance path is the design team using? A WBLCA project and a prescriptive project need very different things from your team.
  • Write it into the contract. Put EPD and quantity requirements into bid packages and subcontracts. If it’s not in the scope, it won’t show up in the submittal.
  • Use a takeoff sheet from day one. Green Badger’s Material Takeoff Sheet and instructions give trades one format for material, manufacturer, quantity, units, and location.
  • Check the data, not just the paperwork. Before you file an EPD, confirm it’s current, matches the product actually installed, and its declared unit aligns with the baseline. An EPD in cubic feet won’t match a baseline in metric tons without a density conversion.
  • Track during construction, not at closeout. Finding out a concrete mix exceeds the CALGreen limit after it’s poured is a problem you can’t fix. Flag it at submittal, while there’s still time to change the mix.

The Bottom Line

Embodied carbon is required now, not optional. LEED v5 makes measuring it a condition of certification. CALGreen makes reducing it a condition of the building permit for a growing number of California projects. Buy Clean policies are pushing in the same direction.

The teams that do well here aren’t the ones with the most sustainability experts. They’re the ones that build embodied carbon into the processes they already run: bid packages, submittals, and procurement.